 |
South Norfolk MP Richard Bacon, a member of the Commons public accounts committee, has said it is unacceptable that a total of 40 years’ worth of delays have been added to 18 of the UK’s 20 largest defence equipment projects since they were approved.
|
|
|
The Nimrod MRA4 aircraft is one of
the MoD's
20 largest projects |
|
Mr Bacon said: “In the last twelve months, 20 of
the MoD’s biggest equipment projects clocked up eight years’ worth of
new delays, the largest slippage of forecast in-service dates since 2003. A total of 483 months have now been
added to the forecast in-service dates of all but two of these
projects since they were approved, equivalent to over 40 years’
worth of delays.
“What’s more, on
current forecasts a quarter of these projects will not meet all of
their key user requirements, meaning they won’t be able to do
everything our soldiers, sailors and airmen need them to do.
“This is
unacceptable. Both the MoD and the defence industry need to show
they have learned from previous projects and do far more to keep a
lid on spiralling time and cost delays.”
Mr Bacon was speaking as the National
Audit Office published its report into the Ministry of Defence’s
20
largest defence equipment projects. The report finds that during the 2007-08 financial
year, forecast costs for these projects rose in aggregate by a
further £205 million over their original budgets while forecast
in-service dates slipped in aggregate by an additional 96 months,
equivalent to eight years’ worth of new delays. This is the largest
slippage of forecast in-service dates
since 2003. The
report also finds that, on current forecasts, a quarter of these
projects will not achieve all of their key performance objectives.
The in-service dates of the 18
projects for which time performance can be
reported
are, in aggregate, 483 months later than expected when they were
approved. This is a 36 per cent increase in their expected
timescales and equivalent to over 40 years’ worth of delays overall.
-
The following projects were
covered by this report; Beyond Visual Range Air-to-Air Missile,
Terrier (armoured engineer vehicles), Soothsayer (electronic
warfare system), Nimrod MRA4 (aircraft), Support Vehicle (cargo
and recovery), Advanced Jet Trainer, Astute Class submarine,
A400M (aircraft), Future Lynx (helicopter), Type 45 Destroyer,
Modernised Target Acquisition Designation Sight/Pilots Night
Vision Sensor, Merlin Mk1 Capability Sustainment Programme,
Sting Ray torpedo, Watchkeeper (unmanned aerial vehicle), Falcon
(communications system), Future Joint Combat Aircraft, Typhoon
Future Capability Programme, Typhoon (aircraft), Next Generation
Light Anti-Armour Weapon, Naval Extremely High Frequency/Super
High Frequency Satellite Communications Terminals.
-
Slippage of forecast in-service
dates since 2003:
|
Year |
Aggregate
in-year slippage of forecast in-service date (months) |
|
2008 |
96 |
|
2007 |
38 |
|
2006 |
33 |
|
2005 |
45 |
|
2004 |
62 |
|
2003 |
144 |
(Source: National
Audit Office Major Project Reports 2008-2003)
-
The National Audit Office analysis
of overall timescale performance is based on 18 projects. The
remaining two are excluded for the following reasons:
-
Future Joint Combat Aircraft is part
of the United States’ Joint Strike Fighter programme and is aligned
with its acquisition lifecycle. The current approval is for the cost
of the System Development and Demonstration phase only and further
approval will be sought for the cost and In-Service Date of the main
procurement phases.
-
The Beyond Visual Range Air-to-Air
Missile project is excluded from the analysis because of the changes
that have been made to the definition of the In‑Service Date.
-
483 months expressed in years is
40 and a quarter years (i.e.
483 ÷ 12 = 40.25). Similarly, 96
months expressed in years is 8 years (i.e.
96 ÷ 12 = 8).
18
December 2008
|
|