![]() |
|||||||
|
Home Local News Parliament Articles Speeches Richard Media South Norfolk Expenses Contact
| Nuclear clean-up costs ‘out of control’, says MP |
![]() |
|||||
“Just over
two years ago the estimated cost of cleaning up the Nuclear
Decommissioning Authority’s 19 sites was £61 billion. This has now
increased by £12 billion to £73 billion. What’s more, cost estimates for
upcoming work kept on increasing, even though they should have been
agreed by now. The Authority must find out why costs are increasing and
bring them under control”. The report finds that
the Authority’s 2007 estimate of the undiscounted future costs of sites
over their remaining lifetime (£73 billion) was almost £12 billion (18
per cent) higher than the estimate made in 2005. The report also finds
that cost estimates on work to be undertaken in the near to medium-term,
which might be expected to have stabilised by now, have risen
significantly over successive iterations. 30 January 2008 At the start of 2006-07 the site and the Authority agreed that the project to build an Intermediate Level Waste Store at Hinkley Point A in Somerset, should be accelerated. Planned work on the project during 2006-07 was therefore increased from £2.1 million to £7.9 million. By the end of the year, however, the site had to cut back expenditure on the project. Work with a budget of £0.4 million was removed from the 2006-07 programme and planned expenditure for 2007-08 was cut from £6.0 million to £0.5 million. These cuts required the site to halt its contract for the store after the contractor had prepared the base for the store but had not started to construct its shell. Halting the contract was expected to bring demobilisation costs of some £0.2 million and a similar level of cost is expected to be incurred in restarting the project. See also:
|
|||||||
| © Richard Bacon 2010 | |||||||